TxDOT Contract 6481-89-001 — Awarded to SOUTHERN SOURCING SOLUTIONS, LLC, Freestone County (2025)
FY25 - Freestone/Leon RipRap - 04
Let date
April 8, 2025
Award amount
$80,276
Bidders
5
| Location | Freestone County · Bryan District · IH0045 |
|---|---|
| Type of work | Material Maintenance Project |
| Awarded to | SOUTHERN SOURCING SOLUTIONS, LLC |
| CCSJ | 6481-89-001 |
More on this contract in GoInfraSight
- all 5 bids ranked, with the spread between them
- unit prices for 8 bid items, bidder by bidder
- how the contract has paid since award, from TxDOT's monthly estimates